Project update: Construction of the Blackjack Mountain 36-inch Water Main Replacement project for Cobb County-Marietta Water Authority (CCMWA)

The contractor has remobilized back to the project site and will begin the Jack and Bore installation underneath Sope Creek at the intersection of Wallace Road and Barnes Mill Road. Due to the rain last week, the contractor will be finishing out drilling and blasting this week at the intersection. They will likely start excavation of the bore pit and possibly begin the underground trenchless jack and bore within the following two weeks.

 