The Sandy Plains Road improvements that continue between Piedmont Road and Ebenezer Road were expected to be finished next month. But that work may not be done until December.
Cobb DOT has an agenda item on next Tuesday’s Board of Commissioners meeting asking for a change order to extend the work until Dec. 20. There is no additional cost involved.
The reasons are similar to what’s prompted a delay in finishing the roundabout at Post Oak Tritt Road and Hembree Road: Utility relocation issues with Atlanta Gas Light and inclement weather.
That project was to have been done by now, at the start of a new school year, but has been extended to next March.
The Sandy Plains Road project has had some other delays as well, not mentioned in Tuesday’s agenda item: In May there was an overnight shutdown of Sandy Plains at Ebenezer for emergency repairs due to a water main break caused by a construction truck hitting a fire hydrant.
There also was an overnight water outage on one side of Sandy Plains last month as part of the construction work.
The contract for the $4.4 million Sandy Plains construction project approved by commissioners in 2017 was awarded to C.W. Matthews Contracting Company, Inc., and includes a raised median, new crosswalks and pedestrian signals and resurfacing.
More on Tuesday’s commissioners meeting, which starts at 9 a.m. in the 2nd floor board room of the Cobb government building (100 Cherokee St., downtown Marietta):