After years of delays, Mabry Park funding finally gets approval

Mabry Park Master Plan, funding for Mabry Park
The Mabry Park Master Plan was approved in 2011, but funding wasn’t provided due to budget cuts during the recession.

On Tuesday, after years of delays, the Cobb Board of Commissioners on Tuesday approved Mabry Park funding. More specifically, they authorized a construction contract that would convert a slice what was once a large farm spread in Northeast Cobb into a major passive park.

The construction contract for $2.85 million was approved unanimously, in a 5-0 vote, a month after the commissioners delayed the vote.

There was little discussion Tuesday about the contract, which was awarded to Integrated Construction and Nobility, Inc.. The park, which will be built on 26.5 acres on Wesley Chapel Road at Sandy Plains Road, is expected to be completed in 2019.

Mabry Park will include walking trails, picnic areas, a community garden, playground areas and more on land that includes a large pond.

The construction will also include the development of a paved road into the park from Wesley Chapel Road. In 2008, the county spent $4.3 million in funding from the 2006 Cobb parks SPLOST to purchase the former farm land owned by Ed and Sue Mabry.

The the land sat dormant during the recession, although a master plan was released in 2011.

While the construction funding came out of the 2016 Cobb government SPLOST, the yearly cost for operating Mabry Park comes out of the county general fund. That was the reason for delaying the vote in October, right before the commissioners held their budget retreat.

Resolving how to pay for recurring expenses from a SPLOST project was one of the subjects at the retreat. A one-time cost of $22,230 for equipment and maintenance tools will be funded after construction is complete.

Mabry Park’s annual operating cost will be $104,992; of that $72,122 will go for staff salaries and benefits, and $31,800 is estimated for yearly supplies and utilities.

 

Get Our Free E-Mail Newsletter!

Every Sunday we round up the week’s top headlines and preview the upcoming week in the East Cobb News Digest. Click here to sign up, and you’re good to go!

Mabry Park construction plans delayed again, will be reconsidered in November

Mabry Park

Not for the first time, Mabry Park construction plans have been put on hold. The three members of the Cobb Board of Commissioners who voted on Tuesday to table the item are pledging that it won’t be for long, but that it must be done.

The Northeast Cobb commissioner who fought long and hard for her community to have a passive park doesn’t think any further delays are necessary, even though this one may be for only a month.

“It’s long overdue,” commissioner JoAnn Birrell said, choking up with emotion and pleading for her colleagues to approve a $2.85 million construction contract at Tuesday’s regular meeting. “I see no reason to hold this.”

By a 3-2 vote, however, the commissioners voted to table approval of the contract, to Integrated Construction and Nobility, Inc., with the measure slated to be taken up again on Nov. 14.

Commission chairman Mike Boyce wants Mabry Park and other projects approved by voters through SPLOST referendums to be reviewed for long-term operations and maintenance costs, since that funding comes out of the annual county budget.

The SPLOST impact statements and a policy proposed by Boyce to govern them are among the topics at a commissioners retreat next week. That’s why Boyce said he sought the delay.

By law, projects approved via SPLOST (Special Local Option Sales Tax) must be funded. How to pay for their recurring expenses has been a vexing one for commissioners, who recently voted to spend $20 million in reserve money to balance the fiscal year 2018 budget.

“The project that got caught between a rock and a hard place is Mabry Park,” Boyce said. “We’re going to commit to these parks, but we have a bigger problem here and we need to solve this now.”

Boyce was supported by East Cobb commissioner Bob Ott, whose district now includes Mabry Park, and Bob Weatherford.

Tabling the Mabry Park contract approval comes a week after the commissioners hotly debated additional funding for the new Sewell Mill Library and Cultural Center, another SPLOST project that has more staff and higher operational costs than the East Marietta Library it is replacing.

The Cobb Department of Parks, Recreation and Cultural Affairs has indicated that once that complete, Mabry Park will incur an initial one-time cost of $22,230 for maintenance tools and equipment. Starting with the fiscal year 2019 budget, ongoing annual expenses are estimated to be $104,922. Of that total, $73,122 will go for staff salaries and benefits, and another $31,800 is projected for utilities and operational supplies.

Birrell cited the decade-long process of SPLOST approval, the development of the park master plan and the formation of the Friends of Mabry Park citizens group, which has raised more than $60,000 to help fund the project, located on 26.5 acres at Wesley Chapel Road and Sandy Plains Road.

JoAnn BIrrell, Mabry Park
Commissioner JoAnn Birrell represented the area around Mabry Park until this year following redistricting. (East Cobb News file photo)

“It’s a crying shame that we’re still discussing the construction of Mabry Park,” she said.

But Ott, who inherited the Mabry Park area this year due to redistricting, said it’s prudent for a delay so the board can work through the impact statement policy.

“We cannot continue to build things and not open them because they’re not funded,” Ott said.

He also pointed to unfinished projects in his district, including Hyde Farm (whose proponents have raised more than $350,000) and shifting $1 million in sidewalk funding as part of a series of “very difficult” decisions that have had to be made because of existing commitments.

Hania Whitfield, a former executive board member of the Friends of Mabry Park, was one of several citizens who spoke Tuesday to urge the commissioners to approve the construction contract.

“Many have lost faith they will be able to use the park,” especially seniors, she said. “There is an indisputable lack of green space access in the Northeast Cobb portion of the county.”

Boyce, supported by parks advocates during his successful campaign last year to oust former chairman Tim Lee, said the need to hammer out an impact statement policy can’t be postponed.

“We have to stop and put this together,” he said. “We have to start with something.

“Once we get this process in place, we will never have this problem again.”

 