Cobb commissioners on Tuesday approved a $690,809 contract for traffic improvements at the intersection of Old Canton Road and Holly Springs Road.
Funding for the project is provided in the 2016 Cobb Special Purpose Local-Option Sales Tax (SPLOST). Glosson was the low bidder against six other companies, and the measure was approved by commissioners on their consent agenda.
A total of $1 million was budgeted for the project, which will include the construction of pedestrian refuge islands, a guardrail, signage and striping at a three-way intersection.
About $170,000 has been spent in initial costs, and another $27,000 will be spent to relocate water lines (to be paid with Cobb Water System funds).
Initially the project called for a roundabout, but that option was removed after feedback from the community and Cobb DOT staff after open house sessions.
What’s shown above is a concept map; to see a larger view click here.
The project is expected to take around six months once construction begins.
Related content
- Ousted Cobb Commission Chairman pledges ‘transition in grace’
- Cobb parks and recreation manager named deputy county manager
- Cobb commissioner-elect: ‘We can overcome every challenge’
- Cobb commissioners revoke Tokyo Valentino business license
Get Our Free E-Mail Newsletter!
Every Sunday we round up the week’s top headlines and preview the upcoming week in the East Cobb News Digest. Click here to sign up, and you’re good to go!