Heavy flooding last September in the East Cobb area caused significant damage to the homes and properties of residents who are still dealing with stormwater-related issues nearly a year later.
The rains also caused Sewell Mill Creek to swell over, as it has done before, onto the low-lying East Cobb Park and Fullers Park.
The front quad of East Cobb Park was severely eroded after water rushed over the flat surface along the creek.
After several months, the streambank area was reworked to produce a crest between the creek and the walking path and front quad. A park bench was relocated to the front, close to a small “free library” box.
Similarly, Cobb Parks and Recreation wants to restore and stabilize a portion of Sewell Mill Creek downstream at nearby Fullers Park that also was affected by those floods.
Doing so, according to an agenda item presented to Cobb commissioners, “will stop further erosion and deterioration of the streambank and enhance the visual experience of those walking in the park.”
On Tuesday, that request was approved unanimously, with funding coming from the new 2022 Cobb SPLOST.
The lowest bidder, Integrated Construction and Nobility, Inc. offered a cost of $199,700 in bidding that took place last fall. Bids went as high as $556,000, but even the lowest bid was more than what county officials estimated for the project.
So they negotiated with the contractor to reduce the project cost to $104,500. The funding source specifically is the Countyside Parks Subsurface Infrastructure account, which is earmarked for $1.5 million over the next six years.
That was one of several individual infrastructure contracts approved Tuesday by commissioners.
Commissioners also ratified a previous decision by Cobb County Manager Jackie McMorris to authorize emergency drainage repairs on Turtle Cove Court in the Somerset subdivision of East Cobb.
Cobb DOT replaced 120 feet of a 36-inch corrugated metal pipe that had failed and caused a sinkhole, threatening the safety of the street. The curb and gutter were also replaced, as were two catch basins and some pavement.
The repairs were completed in July and cost $308,550, with the funding coming from the 2022 Cobb SPLOST Transportation Improvements Plan.
Commissioners also voted to approve sidewalk construction in two areas of Northeast Cobb. One is a half-mile stretch on the north side of Davis Road, between Williams Road and Shallowford Road, for $726,727.
The contractor is Glosson Enterprises and the funding is coming from the 2016 Cobb SPLOST ($568K) and another $129.7K from the Capital Projects Fund Commission District 3 Sidewalk Development.
Glosson also was awarded a $476.7K contract to build a sidewalk on the east side of Shaw Road between Piedmont Road and Woodrush Road. That’s a third of a mile, with $250K coming from the 2016 SPLOST and $204K from the same Capital Projects Fund account.
Related:
- Birrell asks Cobb to delay proposed trash service changes
- Proposed changes to Cobb trash service draw citizen opposition
- $1 billion in 2022 Cobb property tax bills issued; due Oct. 15
- Cobb settles lawsuit with Uber driver; agrees to pay $250K
- Cobb DOT to start Bill Murdock-Pine Road realignment
- East Piedmont Road resurfacing project continues
- East Cobb resurfacing projects OK’d with 2022 SPLOST funds
- Cobb commissioners adopt $1.2 billion fiscal year budget
Get Our Free E-Mail Newsletter!
Every Sunday we round up the week’s top headlines and preview the upcoming week in the East Cobb News Digest. Click here to sign up, and you’re good to go!